Our build was released to construction on July 3rd, but officially they start the process on the Monday (6th). Contractors etc are booked on the Monday. They said it could take 2 weeks to get out on our block....
Wednesday July 8th - levelled
Thursday July 9th - Sand and gravel
Friday July 10th- footings dug
Tuesday July 14th-sewerage/drains/plumbing
Wednesday July 15th- Steel delivered and pest control around pipes
Thursday July 16th - Steelwork put in
Friday July 17th - Slab Poured
They let this sit for 7 days then start the framing work! Can't wait to see this turn into our new home.